| SR NO | DESCRIPTION | UOM | No.of Foundations | Weightage % | Baseline Start Date | Baseline Finish Date | Baseline Duration | Plan Value | Actual Value | Plan Cumm. | Actual Cumm |
|---|---|---|---|---|---|---|---|---|---|---|---|
| A | LIQUEFICATION & FERMENTATION | ||||||||||
| 1 | STRUCTURE COLUMNS FOUNDATIONS | EA | 53 | 10.00% | 06-12-2024 | 24-04-2025 | 139 | 42 | 53 | ||
| 2 | SITE TANK FOUNDATIONS | EA | 17 | 3.00% | 06-12-2024 | 24-04-2025 | 139 | 11 | 10 | ||
| 3 | SHOP EQUIPMENTS | EA | 6 | 2.00% | 06-12-2024 | 24-04-2025 | 139 | 0 | 0 | ||
| 4 | BOUGHT OUT FOUNDATIONS | EA | 50 | 10.00% | 06-12-2024 | 24-04-2025 | 139 | 30 | 6 | ||
| 5 | GRADE / GUTTER / DECK SLAB | EA | 1 | 1.00% | 15-04-2025 | 30-06-2025 | 76 | 0 | 0 | ||
| B | DISTILLATION,EVAPORATION & MSDH | ||||||||||
| 1 | STRUCTURE COLUMNS FOUNDATIONS | EA | 43 | 12.00% | 27-12-2024 | 24-03-2025 | 87 | 43 | 43 | ||
| 2 | SITE TANK FOUNDATIONS | EA | 2 | 1.00% | 27-12-2024 | 12-04-2025 | 106 | 2 | 2 | ||
| 3 | SHOP EQUIPMENTS | EA | 37 | 7.00% | 27-12-2024 | 12-05-2025 | 136 | 0 | 0 | ||
| 4 | BOUGHT OUT FOUNDATIONS | EA | 73 | 12.00% | 27-12-2024 | 12-05-2025 | 136 | 0 | 0 | ||
| 5 | GRADE / GUTTER / DECK SLAB | EA | 1 | 1.00% | 27-12-2024 | 25-06-2025 | 180 | 0 | 1 | ||
| C | RECEIVER AND STORAGE | ||||||||||
| 1 | STRUCTURE COLUMNS FOUNDATIONS | EA | 10 | 2.00% | 06-12-2024 | 24-04-2025 | 139 | 10 | 0 | ||
| 2 | SITE TANK FOUNDATIONS | EA | 23 | 5.00% | 06-12-2024 | 20-03-2025 | 104 | 23 | 0 | ||
| 3 | BOUGHT OUT FOUNDATIONS | EA | 17 | 3.00% | 06-12-2024 | 02-05-2025 | 147 | 8 | 0 | ||
| 4 | DYKE WALL | EA | 1 | 1.00% | 06-12-2024 | 20-05-2025 | 165 | 0 | 0 | ||