| SR NO | DESCRIPTION | UOM | No.of Foundations | Weightage % | Baseline Start Date | Baseline Finish Date | Baseline Duration | Plan Value | Actual Value | Plan Cumm. | Actual Cumm |
|---|---|---|---|---|---|---|---|---|---|---|---|
| A | DISTILLATION,EVAPORATION & MSDH | ||||||||||
| 1 | SITE TANK FOUNDATIONS | EA | 1 | 9.00% | 20-02-2025 | 20-04-2025 | 0 | ||||
| 2 | SHOP EQUIPMENTS | EA | 12 | 15.00% | 10-03-2025 | 30-04-2025 | 0 | ||||
| 3 | BOUGHT OUT FOUNDATIONS | EA | 17 | 15.00% | 10-03-2025 | 20-05-2025 | 0 | ||||
| 4 | GRADE / GUTTER / DECK SLAB | EA | 1 | 5.00% | 10-03-2025 | 20-05-2025 | 0 | ||||
| B | RECEIVER AND STORAGE | ||||||||||
| 1 | SITE TANK FOUNDATIONS | EA | 4 | 20.00% | 20-02-2025 | 20-04-2025 | 0 | ||||
| 2 | BOUGHT OUT FOUNDATIONS | EA | 7 | 5.00% | 10-03-2025 | 20-05-2025 | 0 | ||||
| 3 | DYKE WALL | EA | 1 | 1.00% | 10-03-2025 | 20-06-2025 | 0 | ||||
| C | STRUCTURE FAB & ERE. (CLIENT SCOPE) | ||||||||||
| 1 | RECEIVER AND STORAGE | MT | 12 | 5.00% | 25-03-2025 | 14-05-2025 | 0 | ||||
| 2 | PIPE RACK / YARD STRUCTURE | MT | 15 | 10.00% | 10-04-2025 | 15-05-2025 | 0 | ||||
| 3 | DISTILLATION,EVAPORATION & MSDH | MT | 25 | 15.00% | 15-04-2025 | 28-05-2025 | 0 | ||||