SR NO DESCRIPTION UOM No.of Foundations Weightage % Baseline Start Date Baseline Finish Date Baseline Duration Plan Value Actual Value Plan Cumm. Actual Cumm
A DISTILLATION,EVAPORATION & MSDH
1 SITE TANK FOUNDATIONS EA 1 9.00% 20-02-2025 20-04-2025 0
2 SHOP EQUIPMENTS EA 12 15.00% 10-03-2025 30-04-2025 0
3 BOUGHT OUT FOUNDATIONS EA 17 15.00% 10-03-2025 20-05-2025 0
4 GRADE / GUTTER / DECK SLAB EA 1 5.00% 10-03-2025 20-05-2025 0
B RECEIVER AND STORAGE
1 SITE TANK FOUNDATIONS EA 4 20.00% 20-02-2025 20-04-2025 0
2 BOUGHT OUT FOUNDATIONS EA 7 5.00% 10-03-2025 20-05-2025 0
3 DYKE WALL EA 1 1.00% 10-03-2025 20-06-2025 0
C STRUCTURE FAB & ERE. (CLIENT SCOPE)
1 RECEIVER AND STORAGE MT 12 5.00% 25-03-2025 14-05-2025 0
2 PIPE RACK / YARD STRUCTURE MT 15 10.00% 10-04-2025 15-05-2025 0
3 DISTILLATION,EVAPORATION & MSDH MT 25 15.00% 15-04-2025 28-05-2025 0